An application for a wind turbine nearly 250 foot high on the road to Tenby, recommended to be turned down due to a lack of information on how it could affect bats, has been put on hold.
In an application recommended for refusal at the December meeting of Pembrokeshire County Council’s planning committee, Constantine Wind Energy Ltd sought permission for a 76-metre-high wind turbine at Summerton Farm, Sageston.
Back in 2024, an application to replace a current 60.5m high turbine on the site with one up to 90 metres, or just under 300 foot, at the site was refused on the grounds its height and scale would have a detrimental impact on the visual amenity of the locality, with the additional clause of failing to comply with supplementary guidance.
A report for committee members on the latest application says the smaller turbine than previously proposed, representing a 16-metre increase in height from a previously granted turbine “would not be sufficient for it to become an overbearing feature in the landscape,” with no objections from either the Council Landscape Officer or Natural Resources Wales.
However, concerns were raised by the council ecologist that the applicant’s Preliminary Ecological Appraisal Report was incomplete.
“The Council Ecologist questions why the response received in relation to myotis bat records were not included within the initial PEA. As such, he considers that the PEA does not present enough information on the possible presence of bats within the application site area.
“Whilst there may be negligible foraging and commuting potential, there are records of foraging on grassland within two kilometres which have positive identification of myotis bat foraging, along with greater and lesser horseshoe bat foraging. He also notes that the application site is in close proximity to a wooded area.”
It was recommended for refusal on the grounds that appraisal report, and technical note, “do not adequately address the impact of the proposed wind turbine on bat activity in the area”.
At the committee meeting, members heard the scheme had been temporarily withdrawn to deal with issues raised, the application expected to return to a future meeting.